Maintenance dredging Port of Liverpool

Location Liverpool, England
Client Peel Ports Group Limited
Period 2015, 2016, 2017 and 2019
Equipment used Albatros
Amazone
Kees Jr.
Mahury
Peter
Dredging volume Approx. 350.000 m3 per dredging campaign

About the project

The activities for this contract include:

  • Maintenance dredging in the Liverpool docks by using a TSHD and bed leveller,
  • Transport of the dredged material via the locks to the landfill site in the Mersey River,
  • Conducting Multi-Beam survey work throughout the Liverpool dock system,
  • Plough- and survey work in the Cammel Lairds Shipyard in Birkenhead.

     